Monday, May 30, 2022

XIX: Breaking Ground

Dirt has been moved!  The builder was able to dig out the foundation and have that pass inspection.  Next up concrete—as soon as he gets someone to deliver—hopefully before needing to re-excavate the footers.

In the meantime, the electrical line has to be moved, as it runs over the build site (nothing beyond the foundation can go in with the line there).  To move to line, trees have to come down.  We’re arranging for the tree removal now, and I get to pay the electric company for a new pole.  The company will approve the move after the trees are down, then it takes about four weeks to get a crew to do the moving of the line.